Closing Process Group - ITTO

There are 2 Processes in this Process Group spread over 2 Knowledge areas.

1. Close Process or Phase - I - CPP

2. Close Procurements - P - CP



Closing Process Group

Outputs: 3


Integration Management



Close Project or Phase - CPP


1
Final Product, Service or Result Transition
CPP

2
OPA Updates
CPP
CP

Procurement  Management



Close Procurements - CP


3
Closed Procurements

CP


Inputs: 4

Integration Management



Close Project or Phase - CPP


1
Project Management Plan
CPP
CP
2
Accepted Deliverables
CPP

3
OPA
CPP


Procurement  Management



Close Procurements - CP


4
Procurement Documentation

CP




Tools & Techniques: 4

Integration Management



Close Project or Phase - CPP


1
Expert Judgment
CPP


Procurement  Management



Close Procurements - CP


2
Procurement Audit

CP
3
Negotiated Settlements

CP
4
Records Management System

CP
 