1. Close Process or Phase - I - CPP
2. Close Procurements - P - CP
Closing Process Group
Outputs: 3
Integration Management
|
|||
Close Project or Phase - CPP
|
|||
1
|
Final Product, Service or Result Transition
|
CPP
|
|
2
|
OPA Updates
|
CPP
|
CP
|
Procurement Management
|
|||
Close Procurements - CP
|
|||
3
|
Closed Procurements
|
CP
|
Inputs: 4
Integration Management
|
|||
Close Project or Phase - CPP
|
|||
1
|
Project Management Plan
|
CPP
|
CP
|
2
|
Accepted Deliverables
|
CPP
|
|
3
|
OPA
|
CPP
|
|
Procurement Management
|
|||
Close Procurements - CP
|
|||
4
|
Procurement Documentation
|
CP
|
Tools & Techniques: 4
Integration Management
|
|||
Close Project or Phase - CPP
|
|||
1
|
Expert Judgment
|
CPP
|
|
Procurement Management
|
|||
Close Procurements - CP
|
|||
2
|
Procurement Audit
|
CP
|
|
3
|
Negotiated Settlements
|
CP
|
|
4
|
Records Management System
|
CP
|
No comments: